$A, B$ and $C$ individually can do a work in $10\, days, 12\, days$ and $15\, days,$ respectively. The number of days required to finish the work by $A, B$ and $C$ working together is? (in $days$)

  • A
    $16$
  • B
    $8$
  • C
    $4$
  • D
    $2$

Explore More

Similar Questions

$A$ can complete a work in $10$ days,$B$ can complete the same work in $20$ days,and $C$ in $40$ days. $A$ starts working on the first day,$B$ works on the second day,and $C$ works on the third day. Again,$A$ works on the fourth day,$B$ on the fifth day,and so on. If they continue working in the same way,in how many days will the work be completed?

Difficult
View Solution

$A$ and $B$ can do a work in $8$ days,$B$ and $C$ can do the same work in $12$ days. $A, B$ and $C$ together can finish it in $6$ days. $A$ and $C$ together will do it in (in days):

$A$ certain job was assigned to a group of men to do in $20$ days. But,$12$ men did not turn up for the job and the remaining men did the job in $32$ days. The original number of men in the group was:

$A,$ $B,$ and $C$ can do a work separately in $16,$ $32,$ and $48$ days respectively. They started the work together,but $B$ left $8$ days before and $C$ left $6$ days before the completion of the work. In what time is the work finished? (in days)

$A$ can do a piece of work in $15 \text{ days}$. With the help of $A$,$B$ can do it in $6 \frac{2}{3} \text{ days}$. $B$ can do it alone in (in $\text{days}$)

Vedclass Products

For Students

Vedclass Test Series

Mock tests in real JEE/NEET style with performance analysis. 5-day free trial.

Start Free Trial
For Teachers

Exam Paper Generator

Generate Set A/B/C/D exam papers from 7.5L+ questions in 2 minutes. 3 chapters free.

Try Free
For Institutes

Online Exam Module

Live online exams with unlimited students, 360° analytics & white-label branding.

See Demo