$A$ can do a certain job in $12$ days. $B$ is $60\%$ more efficient than $A$. How many days would $B$ alone take to do the same job?

  • A
    $7\frac{1}{2}$
  • B
    $8$
  • C
    $10$
  • D
    $7$

Explore More

Similar Questions

$A$ and $B$ can do a piece of work in $30$ days,while $B$ and $C$ can do the same work in $24$ days and $C$ and $A$ in $20$ days. They all work together for $10$ days when $B$ and $C$ leave. How many days more will $A$ take to finish the work?

Difficult
View Solution

$A$ and $B$ working separately can do a piece of work in $9$ and $15 \, \text{days}$ respectively. If they work on alternate days beginning with $A$,then the work will be completed in how many days?

$P, Q$ and $R$ can do a piece of work in $60$ days,$100$ days and $80$ days respectively. They work together to finish the work and receive $Rs. 2256$. Then $P$ will get (in $Rs.$)

Difficult
View Solution

If $8$ men or $10$ women can do a piece of work in $50$ days,in what time will $28$ men and $15$ women do it? (in days)

Difficult
View Solution

One man,$3$ women,and $4$ boys can do a work in $96$ hours,$2$ men and $8$ boys can do it in $80$ hours,and $2$ men and $3$ women can do it in $120$ hours. In how many hours can it be done by $5$ men and $12$ boys? (in hours)

Difficult
View Solution

Vedclass Products

For Students

Vedclass Test Series

Mock tests in real JEE/NEET style with performance analysis. 5-day free trial.

Start Free Trial
For Teachers

Exam Paper Generator

Generate Set A/B/C/D exam papers from 7.5L+ questions in 2 minutes. 3 chapters free.

Try Free
For Institutes

Online Exam Module

Live online exams with unlimited students, 360° analytics & white-label branding.

See Demo