$A, B$ and $C$ can complete a piece of work in $6, 12$ and $24$ days respectively. They altogether will complete the work in (in days):

  • A
    $5 \frac{2}{7}$
  • B
    $4 \frac{3}{7}$
  • C
    $3 \frac{3}{7}$
  • D
    none of these

Explore More

Similar Questions

$A$ and $B$ working separately can do a piece of work in $9$ and $15 \, \text{days}$ respectively. If they work on alternate days beginning with $A$,then the work will be completed in how many days?

$A$ is thrice as good a workman as $B$ and therefore is able to finish a job in $60\, days$ less than $B.$ Working together,they can do it in (in $days$)

If $4$ men or $8$ women can do a piece of work in $15$ days,in how many days can $6$ men and $12$ women do the same piece of work?

$A, B$ and $C$ can do a job in $6$ days,$12$ days and $15$ days,respectively. After $\frac{1}{8}$ of the work is completed,$C$ leaves the job. The rest of the work is done by $A$ and $B$ together. The total time taken to finish the work is (in days):

$3$ women and $18$ children together take $2$ days to complete a piece of work. How many days will $9$ children alone take to complete the piece of work,if $6$ women alone can complete the piece of work in $3$ days?

Vedclass Products

For Students

Vedclass Test Series

Mock tests in real JEE/NEET style with performance analysis. 5-day free trial.

Start Free Trial
For Teachers

Exam Paper Generator

Generate Set A/B/C/D exam papers from 7.5L+ questions in 2 minutes. 3 chapters free.

Try Free
For Institutes

Online Exam Module

Live online exams with unlimited students, 360° analytics & white-label branding.

See Demo