$A$ and $B$ can complete a piece of work in $30 \text{ days}$,$B$ and $C$ in $40 \text{ days}$,while $C$ and $A$ in $60 \text{ days}$. $A, B, C$ together can complete the work in (in $\text{days}$):

  • A
    $24 \frac{3}{4}$
  • B
    $28 \frac{2}{3}$
  • C
    $26 \frac{2}{3}$
  • D
    None of these

Explore More

Similar Questions

$B$ would have taken $10 \, \text{hours}$ more than what $A$ would have taken to complete a task if each of them worked alone. Working together they can complete the task in $12 \, \text{hours}$. How many $\text{hours}$ would $B$ take to do $50 \%$ of the task?

Difficult
View Solution

$A$ and $B$ can complete a work in $15$ days and $10$ days respectively. They started doing the work together,but after $2$ days $B$ had to leave and $A$ alone completed the remaining work. In how many days was the whole work completed?

If $10$ men can do a piece of work in $12$ days,the time taken by $12$ men to do the same piece of work will be (in days).

$A$ and $B$ can do a job alone in $12 \text{ days}$ and $15 \text{ days}$ respectively. $A$ starts the work and after $6 \text{ days}$,$B$ also joins to finish the work together. For how many days did $B$ actually work on the job?

$7$ men can complete a piece of work in $12$ days. How many additional men will be required to complete double the work in $8$ days?

Difficult
View Solution

Vedclass Products

For Students

Vedclass Test Series

Mock tests in real JEE/NEET style with performance analysis. 5-day free trial.

Start Free Trial
For Teachers

Exam Paper Generator

Generate Set A/B/C/D exam papers from 7.5L+ questions in 2 minutes. 3 chapters free.

Try Free
For Institutes

Online Exam Module

Live online exams with unlimited students, 360° analytics & white-label branding.

See Demo