$A$ and $B$ can complete a piece of work in $18$ days; $B$ and $C$ in $24$ days; $C$ and $A$ in $36$ days. $A$ alone can complete the work in (in days):

  • A
    $48$
  • B
    $56$
  • C
    $40$
  • D
    none of these

Explore More

Similar Questions

$A$ can complete a work in $6 \, days$ while $B$ can complete the same work in $12 \, days$. If they work together and complete it,the portion of the work done by $A$ is:

Sixteen men can complete a work in $15$ days,$24$ children can do the same work in $20$ days. In how many days will $8$ men and $8$ children complete the same work?

Difficult
View Solution

$A$ alone can complete a work in $18 \, days$ and $B$ alone in $15 \, days.$ $B$ alone worked at it for $10 \, days$ and then left the work. In how many more days will $A$ alone complete the remaining work?

Sakshi can do a piece of work in $20$ days. Tanya is $25\%$ more efficient than Sakshi. The number of days taken by Tanya to do the same piece of work is

Ram and Hari can cut $12 \, kg$ of nuts in $2 \, days$. After $5 \, days$, Hari left the work. Ram took $8$ more days to cut the rest of the nuts. If a total of $58 \, kg$ of nuts were cut, the time taken by Hari to cut $10 \, kg$ of nuts is (in days):

Vedclass Products

For Students

Vedclass Test Series

Mock tests in real JEE/NEET style with performance analysis. 5-day free trial.

Start Free Trial
For Teachers

Exam Paper Generator

Generate Set A/B/C/D exam papers from 7.5L+ questions in 2 minutes. 3 chapters free.

Try Free
For Institutes

Online Exam Module

Live online exams with unlimited students, 360° analytics & white-label branding.

See Demo