$A$ and $B$ together can complete a work in $10$ days. They started together,but $A$ left after $2$ days and the remaining work was completed by $B$ in $12$ days. In how many days can $A$ complete the entire work while working alone?

  • A
    $15$
  • B
    $20$
  • C
    $30$
  • D
    $45$

Explore More

Similar Questions

$A$ track of $100\, m$ can be built by $7\, men$ or $10\, women$ in $70\, days.$ How many days will $14\, men$ and $20\, women$ take to build a track of $600\, m$?

Difficult
View Solution

$A$ does $\frac{4}{5}$ of a work in $20 \, \text{days}$. He then calls in $B$ and they together finish the remaining work in $3 \, \text{days}$. How long would $B$ alone take to do the whole work? (in $\text{days}$)

$A$ farmer can plough a field working $6$ hours per day in $18$ days. How many hours per day must the farmer work to finish the same work in $12$ days?

$5$ men and $5$ women earn $Rs. 660$ in $3$ days. $10$ men and $20$ women earn $Rs. 3500$ in $5$ days. In how many days can $6$ men and $4$ women earn $Rs. 1060$?

$12$ men complete a work in $9$ days. After they have worked for $6$ days,$6$ more men join them. How many days will they take to complete the remaining work?

Difficult
View Solution

Vedclass Products

For Students

Vedclass Test Series

Mock tests in real JEE/NEET style with performance analysis. 5-day free trial.

Start Free Trial
For Teachers

Exam Paper Generator

Generate Set A/B/C/D exam papers from 7.5L+ questions in 2 minutes. 3 chapters free.

Try Free
For Institutes

Online Exam Module

Live online exams with unlimited students, 360° analytics & white-label branding.

See Demo