$A$ does $\frac{2}{5}$ of a work in $9$ days. Then $B$ joined him and they together completed the remaining work in $6$ days. $B$ alone can finish the whole work in (in days):

  • A
    $6 \frac{12}{13}$
  • B
    $8 \frac{2}{11}$
  • C
    $10$
  • D
    $18$

Explore More

Similar Questions

Working efficiencies of $A$ and $B$ for completing a piece of work are in the ratio $3: 4$. The number of days taken by them to complete the work will be in the ratio:

$12$ men complete a work in $9$ days. After they have worked for $6$ days,$6$ more men join them. How many days will they take to complete the remaining work?

Difficult
View Solution

Subhash can copy $50$ pages in $10$ $h$,Subhash and Prakash can copy $300$ pages in $40$ $h$. In how much time can Prakash copy $30$ pages? (in $h$)

To complete a work,$A$ takes $50 \%$ more time than $B$. If together they take $18 \text{ days}$ to complete the work,how much time shall $B$ take to do it? (in days)

$A$ contractor undertakes to dig a canal $12 \, km$ long in $350 \, days$ and employs $45$ men. After $200 \, days$ he finds that only $4.5 \, km$ of the canal has been completed. Find the number of extra men he must employ to finish the work in time (in $men$).

Vedclass Products

For Students

Vedclass Test Series

Mock tests in real JEE/NEET style with performance analysis. 5-day free trial.

Start Free Trial
For Teachers

Exam Paper Generator

Generate Set A/B/C/D exam papers from 7.5L+ questions in 2 minutes. 3 chapters free.

Try Free
For Institutes

Online Exam Module

Live online exams with unlimited students, 360° analytics & white-label branding.

See Demo