$P$ and $Q$ together can do a job in $6$ days. $Q$ and $R$ can finish the same job in $60/7$ days. $P$ started the work and worked for $3$ days. $Q$ and $R$ continued for $6$ days. Then the difference of days in which $R$ and $P$ can complete the job is

  • A
    $12$
  • B
    $10$
  • C
    $8$
  • D
    $15$

Explore More

Similar Questions

$A$ can do a certain work in the same time in which $B$ and $C$ together can do it. If $A$ and $B$ together could do it in $10 \text{ days}$ and $C$ alone in $50 \text{ days}$,then $B$ alone could do it in (in $\text{days}$):

Difficult
View Solution

$5$ men can complete a work in $2$ days,$4$ women can complete the same work in $3$ days and $5$ children can do it in $3$ days. $1$ man,$1$ woman and $1$ child,working together,can complete the work in (in days):

Difficult
View Solution

Four examiners can examine a certain number of answer papers in $10 \, \text{days}$ by working for $5 \, \text{hours}$ a $\text{day}$. For how many $\text{hours}$ in a $\text{day}$ would $2$ examiners have to work in order to examine twice the number of answer papers in $20 \, \text{days}$? (in $\text{hours}$)

Difficult
View Solution

$6$ men or $12$ women can do a piece of work in $20$ days. In how many days can $8$ men and $16$ women do twice as big as this work?

If $8$ men or $10$ women can do a piece of work in $50$ days,in what time will $28$ men and $15$ women do it? (in days)

Difficult
View Solution

Vedclass Products

For Students

Vedclass Test Series

Mock tests in real JEE/NEET style with performance analysis. 5-day free trial.

Start Free Trial
For Teachers

Exam Paper Generator

Generate Set A/B/C/D exam papers from 7.5L+ questions in 2 minutes. 3 chapters free.

Try Free
For Institutes

Online Exam Module

Live online exams with unlimited students, 360° analytics & white-label branding.

See Demo