$A$ and $B$ together can complete a task in $20$ days. $B$ and $C$ together can complete the same task in $30$ days. $A$ and $C$ together can complete the same task in $40$ days. What is the ratio of the number of days taken by $A$ when completing the same task alone to the number of days taken by $C$ when completing the same task alone?

  • A
    $2:5$
  • B
    $2:7$
  • C
    $3:7$
  • D
    $1:5$

Explore More

Similar Questions

$A$ can do a work in $6$ days and $B$ can do the same work in $5$ days. The contract for the work is of $Rs. 220$. How much shall $B$ get if both of them work together? (in $Rs.$)

$A$ does $\frac{1}{5}$ of a work in a $week$. $B$ finishes the same in a fortnight. $B$ starts the work and works only for $3$ days. Thereafter,$A$ completes the job. In how many days will $A$ finish the remaining work?

$A, B$ and $C$ can do a piece of work in $30, 20$ and $10$ days respectively. $A$ is assisted by $B$ on one day and by $C$ on the next day,alternately. How long would the work take to finish? (in days)

Difficult
View Solution

$A$ and $B$ can do a piece of work in $20$ days and $12$ days,respectively. $A$ started the work alone and then after $4$ days $B$ joined him until the completion of the work. How long did the work last? (in days)

Difficult
View Solution

$A$ takes twice as much time as $B$ or thrice as much time as $C$ to finish a piece of work. Working together,they can finish the work in $2$ days. $B$ can do the work alone in (in days):

Vedclass Products

For Students

Vedclass Test Series

Mock tests in real JEE/NEET style with performance analysis. 5-day free trial.

Start Free Trial
For Teachers

Exam Paper Generator

Generate Set A/B/C/D exam papers from 7.5L+ questions in 2 minutes. 3 chapters free.

Try Free
For Institutes

Online Exam Module

Live online exams with unlimited students, 360° analytics & white-label branding.

See Demo