$250$ men can finish a work in $20 \, \text{days}$ working $5 \, \text{hours}$ a day. To finish the work within $10 \, \text{days}$ working $8 \, \text{hours}$ a day,the minimum number of men required is:

  • A
    $310$
  • B
    $300$
  • C
    $313$
  • D
    $312$

Explore More

Similar Questions

If the wages of $45$ women amount to $Rs. 46575$ in $48$ days,how many men must work for $16$ days to receive $Rs. 17250$,given that the daily wage of a man is double that of a woman?

$A$ can do a piece of work in $20$ days and $B$ in $30$ days. They work together for $7$ days and then both leave the work. Then $C$ alone finishes the remaining work in $10$ days. In how many days will $C$ finish the full work?

$A$ can do a work in $5 \, \text{days}$ less than the time taken by $B$ to do it. If both of them together take $11 \frac{1}{9} \, \text{days}$, then the time taken by $B$ alone to do the same work (in $\text{days}$) is

If a job is to be completed in $10 \, \text{days}$,it requires $270 \, \text{persons}$. If $180 \, \text{persons}$ take up the same job,they will finish it in (in $\text{days}$):

$A$ and $B$ complete a job in $12 \text{ days}$,while $A, B$,and $C$ can complete it in $8 \text{ days}$. $C$ alone will finish the job in (in $\text{days}$):

Vedclass Products

For Students

Vedclass Test Series

Mock tests in real JEE/NEET style with performance analysis. 5-day free trial.

Start Free Trial
For Teachers

Exam Paper Generator

Generate Set A/B/C/D exam papers from 7.5L+ questions in 2 minutes. 3 chapters free.

Try Free
For Institutes

Online Exam Module

Live online exams with unlimited students, 360° analytics & white-label branding.

See Demo