$A$ can do a piece of work in $4 \, days$ and $B$ can do it in $12 \, days.$ In how many $days$ will they finish the work,both working together?

  • A
    $2$
  • B
    $3$
  • C
    $4$
  • D
    $6$

Explore More

Similar Questions

$A,$ $B,$ and $C$ have to type $506$ pages to finish an assignment. $A$ can type a page in $12$ minutes,$B$ in $15$ minutes,and $C$ in $24$ minutes. If they divide the task into three parts so that all three of them spend an equal amount of time typing,what is the number of pages that $B$ should type?

$A$ and $B$ can do a work in $12$ days,$B$ and $C$ in $15$ days,and $C$ and $A$ in $20$ days. If $A, B,$ and $C$ work together,they will complete the work in (in days):

$18$ boys can do a piece of work in $24$ days. In how many days can $27$ boys do the same work?

Two workers $A$ and $B$ working together completed a job in $5$ days. If $A$ worked twice as efficiently as he actually did and $B$ worked $1/3$ as efficiently as he actually did,the work would have been completed in $3$ days. To complete the job alone,$A$ would require (in days):

$6$ men or $12$ women can do a piece of work in $20$ days. In how many days can $8$ men and $16$ women do twice as big as this work?

Vedclass Products

For Students

Vedclass Test Series

Mock tests in real JEE/NEET style with performance analysis. 5-day free trial.

Start Free Trial
For Teachers

Exam Paper Generator

Generate Set A/B/C/D exam papers from 7.5L+ questions in 2 minutes. 3 chapters free.

Try Free
For Institutes

Online Exam Module

Live online exams with unlimited students, 360° analytics & white-label branding.

See Demo