$A$ and $B$ together can complete a work in $3$ days. They start together,but after $2$ days,$B$ left the work. If the work is completed after two more days,in how many days would $B$ alone do the work?

  • A
    $5$
  • B
    $6$
  • C
    $9$
  • D
    $10$

Explore More

Similar Questions

$A$ and $B$ can complete a work in $15$ days and $10$ days respectively. They started doing the work together,but after $2$ days $B$ had to leave and $A$ alone completed the remaining work. In how many days was the whole work completed?

$A$ and $B$ can separately do a piece of work in $6 \, \text{days}$ and $12 \, \text{days}$ respectively. How long will they together take to do the work? (in $\text{days}$)

$A$ team of $30$ men is supposed to do a work in $38$ days. After $25$ days,$5$ more men were employed and the work was finished one day earlier. How many days would it have been delayed if $5$ more men were not employed? (in days)

Twenty women together can complete a work in $16$ days. $16$ men together can complete the same work in $15$ days. The ratio of the working capacity of a man to that of a woman is

$A$ contractor has the target of completing a work in $40 \text{ days}$. He employed $20$ persons who completed $\frac{1}{4}$ of the work in $10 \text{ days}$ and left. The number of additional persons he has to employ to finish the remaining part of the work as per the target is:

Vedclass Products

For Students

Vedclass Test Series

Mock tests in real JEE/NEET style with performance analysis. 5-day free trial.

Start Free Trial
For Teachers

Exam Paper Generator

Generate Set A/B/C/D exam papers from 7.5L+ questions in 2 minutes. 3 chapters free.

Try Free
For Institutes

Online Exam Module

Live online exams with unlimited students, 360° analytics & white-label branding.

See Demo