$A$ and $B$ can complete a piece of work in $30 \text{ days}$,$B$ and $C$ can complete the same work in $20 \text{ days}$,and $A$ and $C$ can complete it in $15 \text{ days}$. If all of them work together,the time taken to complete the work will be? (in $days$)

  • A
    $10$
  • B
    $12$
  • C
    $12 \frac{2}{3}$
  • D
    $13 \frac{1}{3}$

Explore More

Similar Questions

Ram can finish a work in $15 \text{ days}$ working $8 \text{ hrs/day}$. Fari can finish it in $6 \frac{2}{3} \text{ days}$ at $9 \text{ hrs/day}$. Find in how many days both can finish it together,if both work $10 \text{ hrs/day}$?

If $12$ men or $18$ women can build a wall in $14$ days,then working at the same rate,$8$ men and $16$ women can build the same wall in how many days?

The total number of men,women,and children working in a factory is $18$. They earn $Rs. 4000$ in a day. If the sum of the wages of all men,all women,and all children is in the ratio $18: 10: 12$,and the wages of an individual man,woman,and child are in the ratio $6: 5: 3$,then how much does a woman earn in a day? (in $Rs.$)

$A$ can do a work in $5 \, \text{days}$ less than the time taken by $B$ to do it. If both of them together take $11 \frac{1}{9} \, \text{days}$, then the time taken by $B$ alone to do the same work (in $\text{days}$) is

$A$ and $B$ can do a piece of work in $30$ days,while $B$ and $C$ can do the same work in $24$ days and $C$ and $A$ in $20$ days. They all work together for $10$ days when $B$ and $C$ leave. How many days more will $A$ take to finish the work?

Difficult
View Solution

Vedclass Products

For Students

Vedclass Test Series

Mock tests in real JEE/NEET style with performance analysis. 5-day free trial.

Start Free Trial
For Teachers

Exam Paper Generator

Generate Set A/B/C/D exam papers from 7.5L+ questions in 2 minutes. 3 chapters free.

Try Free
For Institutes

Online Exam Module

Live online exams with unlimited students, 360° analytics & white-label branding.

See Demo