$45$ men can complete a work in $16$ days. Four days after they started working,$36$ more men joined them. How many days will they now take to complete the remaining work?

  • A
    $6$
  • B
    $8$
  • C
    $6\frac{2}{3}$
  • D
    $7\frac{3}{4}$

Explore More

Similar Questions

$A$ man is twice as fast as a woman and a woman is twice as fast as a boy in doing a work. If all of them, a man, a woman and a boy, can finish the work in $7$ days, in how many days will a boy do it alone?

$P$ can do a piece of work in $9$ days. $Q$ is $50\%$ more efficient than $P$. The number of days it takes for $Q$ to do the same piece of work is

$A$ can finish a work in $18$ days and $B$ can do the same work in $15$ days. $B$ worked for $10$ days and left the job. In how many days can $A$ alone finish the remaining work?

If $10$ men can do a piece of work in $12$ days,the time taken by $12$ men to do the same piece of work will be (in days).

$A$ completes a piece of work in $4 \text{ days}$ and $B$ completes it in $6 \text{ days}$. If they both work on it together,then the number of days required to complete the same work is (in $\text{days}$):

Vedclass Products

For Students

Vedclass Test Series

Mock tests in real JEE/NEET style with performance analysis. 5-day free trial.

Start Free Trial
For Teachers

Exam Paper Generator

Generate Set A/B/C/D exam papers from 7.5L+ questions in 2 minutes. 3 chapters free.

Try Free
For Institutes

Online Exam Module

Live online exams with unlimited students, 360° analytics & white-label branding.

See Demo