$A$ can do a work in $15\, days$ and $B$ in $20\, days.$ If they work on it together for $4\, days,$ then the fraction of the work that is left is

  • A
    $1/4$
  • B
    $1/10$
  • C
    $7/15$
  • D
    $8/15$

Explore More

Similar Questions

$7$ men can complete a piece of work in $12$ days. How many additional men will be required to complete double the work in $8$ days?

Difficult
View Solution

$A$ is $20\%$ more efficient than $B$. If $B$ alone can complete a piece of work in $12$ days,then $A$ alone can complete the same work in how many days?

$A, B$ and $C$ can complete a piece of work in $6, 12$ and $24$ days respectively. They altogether will complete the work in (in days):

Difficult
View Solution

$A$ and $B$ can complete a piece of work in $45$ and $40$ days,respectively. They began the work together,but $A$ leaves after some days and $B$ completed the remaining work in $23$ days. After how many days did $A$ leave?

$A$ can do a work in $15 \text{ days}$ and $B$ in $20 \text{ days}$. If they work together on it for $4 \text{ days}$,then the fraction of the work that is left is

Vedclass Products

For Students

Vedclass Test Series

Mock tests in real JEE/NEET style with performance analysis. 5-day free trial.

Start Free Trial
For Teachers

Exam Paper Generator

Generate Set A/B/C/D exam papers from 7.5L+ questions in 2 minutes. 3 chapters free.

Try Free
For Institutes

Online Exam Module

Live online exams with unlimited students, 360° analytics & white-label branding.

See Demo