$P$ can complete a work in $12$ days working $8$ hours a day. $Q$ can complete the same work in $8$ days working $10$ hours a day. If both $P$ and $Q$ work together,working $8$ hours a day,in how many days can they complete the work?

  • A
    $5 \frac{5}{11}$
  • B
    $5 \frac{6}{11}$
  • C
    $6 \frac{5}{11}$
  • D
    $6 \frac{6}{11}$

Explore More

Similar Questions

$A$ and $B$ together can complete a work in $8$ days. $B$ alone can complete that work in $12$ days. $B$ alone worked for $4$ days. After that,how long will $A$ alone take to complete the remaining work?

$A$ can do a work in $5 \, \text{days}$ less than the time taken by $B$ to do it. If both of them together take $11 \frac{1}{9} \, \text{days}$, then the time taken by $B$ alone to do the same work (in $\text{days}$) is

$A$ can do a piece of work in $12$ days and $B$ in $15$ days. They work together for $5$ days and then $B$ leaves. The number of days taken by $A$ to finish the remaining work is:

$A$ and $B$ can separately complete a piece of work in $20$ days and $30$ days respectively. They worked together for some time,then $B$ left the work. If $A$ completed the rest of the work in $10$ days,then for how many days did $B$ work?

Two workers $A$ and $B$ working together completed a job in $5$ days. If $A$ worked twice as efficiently as he actually did and $B$ worked $\frac{1}{3}$ as efficiently as he actually did,the work would have completed in $3$ days. Find the time for $A$ to complete the job alone (in days).

Vedclass Products

For Students

Vedclass Test Series

Mock tests in real JEE/NEET style with performance analysis. 5-day free trial.

Start Free Trial
For Teachers

Exam Paper Generator

Generate Set A/B/C/D exam papers from 7.5L+ questions in 2 minutes. 3 chapters free.

Try Free
For Institutes

Online Exam Module

Live online exams with unlimited students, 360° analytics & white-label branding.

See Demo