$A$ can do a piece of work in $12$ days and $B$ in $15$ days. They work together for $5$ days and then $B$ leaves. The number of days taken by $A$ to finish the remaining work is:

  • A
    $3$
  • B
    $5$
  • C
    $10$
  • D
    $12$

Explore More

Similar Questions

$39$ persons can repair a road in $12$ days working $5$ hours per day. In how many days will $30$ persons working $6$ hours per day complete the same work?

$A$ man can do a work in $10\, days$. With the help of a boy,he can do the same work in $6\, days$. If they get $Rs.\, 50$ for that work,what is the share of that boy? (in $Rs.$)

If $12$ men and $16$ boys can do a piece of work in $5 \, \text{days}$,and $13$ men and $24$ boys can do it in $4 \, \text{days}$,then the ratio of the daily work done by a man to that of a boy is:

Machine $P$ can print one lakh books in $8$ hours,machine $Q$ can print the same number of books in $10$ hours,while machine $R$ can print them in $12$ hours. All the machines are started at $9.00$ a.m. while machine $P$ is closed at $11.00$ a.m. and the remaining two machines complete the work. Approximately at what time will the work be finished?

Difficult
View Solution

Two men,$A$ and $B$,working together,completed a piece of work. If worked individually,it would have taken them $30$ and $40$ days to complete the work. If they have received a payment of $Rs. 2100$,then $B$'s share is (in $Rs.$)

Vedclass Products

For Students

Vedclass Test Series

Mock tests in real JEE/NEET style with performance analysis. 5-day free trial.

Start Free Trial
For Teachers

Exam Paper Generator

Generate Set A/B/C/D exam papers from 7.5L+ questions in 2 minutes. 3 chapters free.

Try Free
For Institutes

Online Exam Module

Live online exams with unlimited students, 360° analytics & white-label branding.

See Demo