$A$ can do a work in $12$ days. When he had worked for $3$ days,$B$ joined him. If they complete the work in $3$ more days,in how many days can $B$ alone finish the work?

  • A
    $6$
  • B
    $12$
  • C
    $4$
  • D
    $8$

Explore More

Similar Questions

$A$ and $B$ working separately can do a piece of work in $9$ and $15 \, \text{days}$ respectively. If they work on alternate days beginning with $A$,then the work will be completed in how many days?

$A$ and $B$ together can complete a work in $12$ days. $A$ alone can complete it in $20$ days. If $B$ does the work only for half a day daily,then in how many days will $A$ and $B$ together complete the work?

$A$ alone would take $27 \, \text{days}$ more to complete the job than if both $A$ and $B$ worked together. If $B$ worked alone, he would take $3 \, \text{days}$ more to complete the job than $A$ and $B$ working together. What time would they take if both $A$ and $B$ worked together? (in $\text{days}$)

Four examiners can examine a certain number of answer papers in $10$ days by working for $5$ hours a day. For how many hours in a day would $2$ examiners have to work in order to examine twice the number of answer papers in $20$ days?

$2$ men and $1$ woman can do a piece of work in $14$ days,while $4$ women and $2$ men can do the same work in $8$ days. If a man gets $Rs. 90$ per day,what should be the wages per day of a woman? (in $Rs.$)

Difficult
View Solution

Vedclass Products

For Students

Vedclass Test Series

Mock tests in real JEE/NEET style with performance analysis. 5-day free trial.

Start Free Trial
For Teachers

Exam Paper Generator

Generate Set A/B/C/D exam papers from 7.5L+ questions in 2 minutes. 3 chapters free.

Try Free
For Institutes

Online Exam Module

Live online exams with unlimited students, 360° analytics & white-label branding.

See Demo