$A$ work can be completed by $P$ and $Q$ in $12$ days,$Q$ and $R$ in $15$ days,and $R$ and $P$ in $20$ days. In how many days can $P$ alone finish the work?

  • A
    $10$
  • B
    $20$
  • C
    $30$
  • D
    $60$

Explore More

Similar Questions

$4$ men and $6$ women together can complete a work in $8$ days,while $3$ men and $7$ women together can complete it in $10$ days. $20$ women working together will complete it in (in days):

$A$ and $B$ can complete a piece of work in $45$ and $40$ days,respectively. They began the work together,but $A$ leaves after some days and $B$ completed the remaining work in $23$ days. After how many days did $A$ leave?

$A$ takes $10\, \text{days}$ less than the time taken by $B$ to finish a piece of work. If both $A$ and $B$ can do it in $12\, \text{days}$, then the time taken by $B$ alone to finish the work is (in $\text{days}$)

$A$ job can be completed by $12$ men in $12$ days. How many extra days will be needed to complete the job if $6$ men leave after working for $6$ days?

$10$ men can cut $15$ trees in $2$ hours. If $2$ men leave the job,how many trees will be cut in $3$ hours?

Vedclass Products

For Students

Vedclass Test Series

Mock tests in real JEE/NEET style with performance analysis. 5-day free trial.

Start Free Trial
For Teachers

Exam Paper Generator

Generate Set A/B/C/D exam papers from 7.5L+ questions in 2 minutes. 3 chapters free.

Try Free
For Institutes

Online Exam Module

Live online exams with unlimited students, 360° analytics & white-label branding.

See Demo