$A$ job can be completed by $12$ men in $12$ days. How many extra days will be needed to complete the job if $6$ men leave after working for $6$ days?

  • A
    $3$
  • B
    $6$
  • C
    $12$
  • D
    $24$

Explore More

Similar Questions

$A$ and $B$ can complete a piece of work in $15$ days and $10$ days respectively. They contracted to complete the work for $Rs. 30000$. The share of $A$ in the contracted money will be (in $Rs.$)

$A$ does half as much work as $B$ in $three-fourths$ of the time. If together they take $18$ days to complete a work,how much time shall $B$ take to do it alone? (in days)

$P$ can do $\left(\frac{1}{4}\right)$ of the work in $10$ days. $Q$ can do $40\%$ of the work in $40$ days and $R$ can do $\left(\frac{1}{3}\right)$ of the work in $13$ days. Who will complete the work first?

$A$ can do a work in $20 \, \text{days}$ and $B$ in $40 \, \text{days}$. If they work on it together for $5 \, \text{days}$, then the fraction of the work that is left is:

$A$ and $B$ can do a piece of work in $30$ and $36$ days respectively. They began the work together,but $A$ leaves after some days and $B$ finished the remaining work in $25$ days. After how many days did $A$ leave?

Difficult
View Solution

Vedclass Products

For Students

Vedclass Test Series

Mock tests in real JEE/NEET style with performance analysis. 5-day free trial.

Start Free Trial
For Teachers

Exam Paper Generator

Generate Set A/B/C/D exam papers from 7.5L+ questions in 2 minutes. 3 chapters free.

Try Free
For Institutes

Online Exam Module

Live online exams with unlimited students, 360° analytics & white-label branding.

See Demo