$7$ men can complete a piece of work in $12$ days. How many additional men will be required to complete double the work in $8$ days?

  • A
    $28$
  • B
    $21$
  • C
    $14$
  • D
    $7$

Explore More

Similar Questions

Sixteen men can complete a work in $15$ days,$24$ children can do the same work in $20$ days. In how many days will $8$ men and $8$ children complete the same work?

Difficult
View Solution

$A$ tyre has two punctures. The first puncture alone would have made the tyre flat in $9 \,minutes$ and the second alone would have done it in $6 \,minutes.$ If air leaks out at a constant rate,how long does it take both the punctures together to make it flat? (in $minutes$)

$A$ and $B$ together can do a piece of work in $30$ days. $B$ and $C$ together can do it in $20$ days. $A$ starts the work and works on it for $5$ days,then $B$ takes over and works for $15$ days. Finally,$C$ finishes the work in $18$ days. The number of days in which $C$ alone can do the work is (in days):

Difficult
View Solution

Bindal can finish a work in $10$ days. Jindal is twice as efficient as Bindal. If they work together,in how many days will the work be completed?

$45$ men complete a piece of work in $30$ days working $12$ hours a day. In how many days will $60$ men complete the work working $10$ hours a day?

Vedclass Products

For Students

Vedclass Test Series

Mock tests in real JEE/NEET style with performance analysis. 5-day free trial.

Start Free Trial
For Teachers

Exam Paper Generator

Generate Set A/B/C/D exam papers from 7.5L+ questions in 2 minutes. 3 chapters free.

Try Free
For Institutes

Online Exam Module

Live online exams with unlimited students, 360° analytics & white-label branding.

See Demo