$A$ contract is to be completed in $92$ days and $234$ men were set to work,each working $16$ hours a day. After $66$ days,$\frac{4}{7}$ of the work is completed. How many additional men may be employed,so that the work may be completed in time,each man now working $18$ hours a day?

  • A
    $162$
  • B
    $234$
  • C
    $262$
  • D
    $81$

Explore More

Similar Questions

$A, B$ and $C$ individually can do a work in $10\, days, 12\, days$ and $15\, days,$ respectively. The number of days required to finish the work by $A, B$ and $C$ working together is? (in $days$)

$A$ can do a work in $15 \text{ days}$ and $B$ in $20 \text{ days}$. If they work together on it for $4 \text{ days}$,then the fraction of the work that is left is

$A, B$ and $C$ can complete a piece of work in $15, 30$ and $40$ days respectively. They started the work together,but $A$ left $2$ days before the completion of the work and $B$ left $4$ days before the completion of the work. In how many days was the work completed?

$A$ and $B$ can do a piece of work in $8$ days,$B$ and $C$ can do the same work in $12$ days,and $A, B,$ and $C$ together complete it in $6$ days. The number of days required to finish the work by $A$ and $C$ together is:

Difficult
View Solution

$A$ can complete a work in $10$ days,$B$ in $12$ days,and $C$ in $15$ days. All of them began the work together; but $A$ had to leave the work after $2$ days of the start and $B$ also left $3$ days before the completion of the work. How long did the work last? (in days)

Vedclass Products

For Students

Vedclass Test Series

Mock tests in real JEE/NEET style with performance analysis. 5-day free trial.

Start Free Trial
For Teachers

Exam Paper Generator

Generate Set A/B/C/D exam papers from 7.5L+ questions in 2 minutes. 3 chapters free.

Try Free
For Institutes

Online Exam Module

Live online exams with unlimited students, 360° analytics & white-label branding.

See Demo