$A$ contract on a construction job specifies a penalty for delay of completion beyond a certain date as follows: ₹ $200$ for the first day,₹ $250$ for the second day,₹ $300$ for the third day,etc. The penalty for each succeeding day is ₹ $50$ more than for the preceding day. How much money does the contractor have to pay as a penalty if he has delayed the work by $30$ days?

  • A
    $27743$
  • B
    $27891$
  • C
    $27653$
  • D
    $27750$

Explore More

Similar Questions

For the following $APs,$ $3, 1, -1, -3, \ldots$ write the first term and the common difference.

Do $1, 1, 1, 2, 2, 2, 3, 3, 3, \ldots$ form an $AP$? If they form an $AP$,write the next two terms.

An $AP$ consists of $50$ terms of which the $3^{rd}$ term is $12$ and the last term is $106$. Find the $29^{th}$ term.

Difficult
View Solution

For the following $APs,$ write the first term and the common difference: $0.6, 1.7, 2.8, 3.9, \ldots$

For what value of $n$,are the $n^{th}$ terms of two $APs: 63, 65, 67, \ldots$ and $3, 10, 17, \ldots$ equal?

Vedclass Products

For Students

Vedclass Test Series

Mock tests in real JEE/NEET style with performance analysis. 5-day free trial.

Start Free Trial
For Teachers

Exam Paper Generator

Generate Set A/B/C/D exam papers from 7.5L+ questions in 2 minutes. 3 chapters free.

Try Free
For Institutes

Online Exam Module

Live online exams with unlimited students, 360° analytics & white-label branding.

See Demo