$A$ can do a piece of work in $20 \, \text{days}$ and $B$ in $30 \, \text{days}$. They work together for $7 \, \text{days}$ and then, both leave the work. Then, $C$ alone finishes the remaining work in $10 \, \text{days}$. In how many $\text{days}$ will $C$ finish the full work?

  • A
    $25$
  • B
    $30$
  • C
    $24$
  • D
    $20$

Explore More

Similar Questions

$A, B$ and $C$ completed a work costing $Rs. 1800$. $A$ worked for $6$ days,$B$ for $4$ days and $C$ for $9$ days. If their daily wages are in the ratio of $5: 6: 4$,how much amount will be received by $A$ (in $Rs.$)?

Rohan and Mohit can build a wall in $8 \, days$,Mohit and Vikas can build the same wall in $10 \, days$,and Vikas and Rohan can build the same in $12 \, days$. In how many days can all three complete the same wall while working together?

Difficult
View Solution

$A$ and $B$,working together,can complete a piece of work in $12$ days. $B$ and $C$ working together can complete the same piece of work in $16$ days. $A$ worked at it for $5$ days and $B$ worked at it for $7$ days. $C$ finished the remaining work in $13$ days. How many days would $C$ alone take to complete it?

Difficult
View Solution

$4$ men or $6$ women can finish a piece of work in $20$ days. In how many days can $6$ men and $11$ women finish the same work?

$A$ carpenter can build a cupboard in $48 \, \text{hours}$. After $12 \, \text{hours}$, he takes a break. What fraction of the cupboard is yet to be built?

Vedclass Products

For Students

Vedclass Test Series

Mock tests in real JEE/NEET style with performance analysis. 5-day free trial.

Start Free Trial
For Teachers

Exam Paper Generator

Generate Set A/B/C/D exam papers from 7.5L+ questions in 2 minutes. 3 chapters free.

Try Free
For Institutes

Online Exam Module

Live online exams with unlimited students, 360° analytics & white-label branding.

See Demo