$A$ and $B$,working together,can complete a piece of work in $12$ days. $B$ and $C$ working together can complete the same piece of work in $16$ days. $A$ worked at it for $5$ days and $B$ worked at it for $7$ days. $C$ finished the remaining work in $13$ days. How many days would $C$ alone take to complete it?

  • A
    $10$
  • B
    $24$
  • C
    $32$
  • D
    $40$

Explore More

Similar Questions

$P$ can do a piece of work in $9$ days. $Q$ is $50\%$ more efficient than $P$. The number of days it takes for $Q$ to do the same piece of work is

$2$ men and $5$ women can finish a piece of work in $12$ days. $5$ men and $2$ women can finish the same work in $9$ days. In how many days can $3$ women finish the same work?

$A$ and $B$ together can complete a task in $20$ days. $B$ and $C$ together can complete the same task in $30$ days. $A$ and $C$ together can complete the same task in $40$ days. What is the ratio of the number of days taken by $A$ when completing the same task alone to the number of days taken by $C$ when completing the same task alone?

Difficult
View Solution

$4$ mat-weavers can weave $4$ mats in $4$ days. At the same rate,how many mats would be woven by $8$ mat-weavers in $8$ days?

$A$ man,a woman,and a boy can together complete a piece of work in $3$ days. If a man alone can do it in $6$ days and a boy alone in $18$ days,how long will a woman alone take to complete the work? (in days)

Vedclass Products

For Students

Vedclass Test Series

Mock tests in real JEE/NEET style with performance analysis. 5-day free trial.

Start Free Trial
For Teachers

Exam Paper Generator

Generate Set A/B/C/D exam papers from 7.5L+ questions in 2 minutes. 3 chapters free.

Try Free
For Institutes

Online Exam Module

Live online exams with unlimited students, 360° analytics & white-label branding.

See Demo