Solve the following linear programming problem graphically:
Maximise $Z = 4x + y$......$(1)$
subject to the constraints:
${x + y \leqslant 50}$.......$(2)$
${3x + y \leqslant 90}$......$(3)$
${x \geqslant 0, y \geqslant 0}$......$(4)$

  • A
    $120$
  • B
    $110$
  • C
    $50$
  • D
    $0$

Explore More

Similar Questions

$A$ production unit makes a special type of metal chip by combining copper and brass. The standard weight of the chip must be at least $5 \text{ gms}$. The basic ingredients,i.e.,copper and brass,cost $₹8$ and $₹5$ per $\text{gm}$ respectively. Durability considerations dictate that the metal chip must not contain more than $4 \text{ gms}$ of brass and should contain a minimum of $2 \text{ gms}$ of copper. Then,the minimum cost of the metal chip satisfying the above conditions is:

$A$ manufacturing company makes two models $A$ and $B$ of a product. Each piece of Model $A$ requires $9$ labour hours for fabricating and $1$ labour hour for finishing. Each piece of Model $B$ requires $12$ labour hours for fabricating and $3$ labour hours for finishing. For fabricating and finishing,the maximum labour hours available are $180$ and $30$ respectively. The company makes a profit of Rs $8000$ on each piece of model $A$ and Rs $12000$ on each piece of Model $B$. How many pieces of Model $A$ and Model $B$ should be manufactured per week to realise a maximum profit? What is the maximum profit per week?

Difficult
View Solution

Cake-$A$ requires $200\, g$ of flour and $25\, g$ of fat. Cake-$B$ requires $100\, g$ of flour and $50\, g$ of fat. Find the maximum number of cakes which can be made from $5\, kg$ of flour and $1\, kg$ of fat. The mathematical form of this $LPP$ is $.....$

The maximum value of $Z=10 x+25 y$ subject to $0 \leq x \leq 3, 0 \leq y \leq 3, x+y \leq 5, x \geq 0, y \geq 0$ is

$A$ factory manufactures two types of screws, $A$ and $B$. Each type of screw requires the use of two machines, an automatic and a hand-operated one. It takes $4 \, \text{minutes}$ on the automatic and $6 \, \text{minutes}$ on the hand-operated machine to manufacture a package of screws $A$, while it takes $6 \, \text{minutes}$ on the automatic and $3 \, \text{minutes}$ on the hand-operated machine to manufacture a package of screws $B$. Each machine is available for at most $4 \, \text{hours}$ on any day. The manufacturer can sell a package of screws $A$ at a profit of $Rs. \, 7$ and screws $B$ at a profit of $Rs. \, 10$. Assuming that he can sell all the screws he manufactures, how many packages of each type should the factory owner produce in a day in order to maximize his profit? Determine the maximum profit.

Difficult
View Solution

Vedclass Products

For Students

Vedclass Test Series

Mock tests in real JEE/NEET style with performance analysis. 5-day free trial.

Start Free Trial
For Teachers

Exam Paper Generator

Generate Set A/B/C/D exam papers from 7.5L+ questions in 2 minutes. 3 chapters free.

Try Free
For Institutes

Online Exam Module

Live online exams with unlimited students, 360° analytics & white-label branding.

See Demo